In the first phase of the project, two 12t/h biomass gasifiers were built and two 12t/h steam boiler heating projects were built. The construction was officially started in mid-November 2018 and the construction was successfully ignited in early 2019, and it is now running smoothly. According to on-site staff, a single gasifier can supply heating steam up to about 12t/h, and the pressure is stable at about 8kg, which can well meet the heat demand of customers.
In the second phase of the project, a 20t/h biomass gasifier started construction in the second half of 2019 and is now operating smoothly.
Project display
The project site | Nantong, Jiangsu (Printing and Dyeing) |
Heating design | ①2station12tons gasifier with2sets of12tons of steam/hsteam boiler ②1station15Dun gasifier with1 Taiwan900million kcal conducting oil furnace |
Heating requirements | 24h/d 300days/year |
Production date | 2019Nian4 months, and 2020Nian4months |
Steam quality requirements | <p style="margin-right:0;margin-left:0" ≥200tons/day |
Project instruction | The project occupies a compact area, and the three sets of gasifier equipment are reasonably designed to reduce equipment inspections. |
The raw material consumption of a single project is 200 tons/day
Figure 1 (1) 2×12t/h biomass gasifier (Phase I)
Figure 1 (2) Biomass gasifier (Phase II)
Figure 2 Gasifier safety warning
Figure 3 Twisted-cage feeder for gasifier
Figure 4 12t/h biomass gas steam boiler
Figure 5 Control room console
Figure 6 Biomass raw material stockyard